تعداد اسلایدهای پاورپوینت: 35 اسلاید

محمدرضا

صفحه 1:
Master Production Scheduling

صفحه 2:
Master Production Schedule ™ Provides basis for: — Making good use of manufacturing resources — Making customer delivery promises — Resolving tradeoffs between sales and manufacturing — Attaining strategic objectives in the sales and operations plan

صفحه 3:
What is “Master Production cheduling?” = Start with Aggregate plan — (Aggregate Sales & Ops Plan) — Output level designed to meet targets " Disaggregates ™ Converts into specific schedule for each item

صفحه 4:
S&OP vs MPS = “The role of the sales and operations plan is to balance supply and demand volume, while the MPS specifies the mix and volume of the output” ™ MPS shows when products will be available in future ™ Planned production, not forecast

صفحه 5:
Master Production Scheduling Techniques ™ Available = inventory position at end of week =" = starting inventory + MPS - forecast Plan to have positive inventory level — Buffer in case production below plan — Or demand higher than anticipated MPS row is amount to make, MRP system has to figure out how to make it

صفحه 6:
Figure 6.2 ™ Level demand, level production (iS aie Mk ke A= © = COO 11 ‏لسمسمسطا۱‎ 000000000000 ۹ ۹۹ 68 e 27 ‏لته نت۱‎ ۱۱۱۳۹۱۳۹۱2۱ ۱۱ 6020 OKC) 000000000000 000 000 000 |0000| 000 | 000 | 000 | 00 8 Oa kerrd (start) 0

صفحه 7:
0 AE ZlBInIR Figure 6.3 © © 2 © © 0 9 9 0 9ب هص ] غ © © 9 99 ا 20022505100500 | مد اسب دا ‎Gz) 2292222221212 111010100‏ 0 | " Different sales forecast = Same total: 120 units, starts lower, goes higher ™ Level production plan

صفحه 8:
Figure 6.4 عِ © 24 متا LOST Seto ‏نگ‎ SS 5 ‏لت کت ندال‎ ™ Same demand as 6.3 ™ Production adjusts to meet demand = “Chase” production strategy

صفحه 9:
Figure 6.5 لمتكا aitable (Bactery) Ogre Coker ‏ال‎ | € = Lot size of 30 units ™ Produce if projected balance falls below 5 Tae) ™ Extra on-hand inventory is “cycle stock” = 5 unit “trigger” is safety stock

صفحه 10:
AAG Figure 6.5a - next كت اننا 214۱ 8 تخت 7 8 أو ا كك 0 ‎Caracal‏ ‏ا اك كك ا 11 ‎COO 00 50 Re: . (۵0‏ 4( تحت هت ادن 8) ™ Demand in week 1 was 10 ™ Marketing decides forecast was incorrect ™ Raise forecasts to 10 for weeks 2-6 ‏ل‎ 9 Available for wk 2 projected to e — Need to produce in week 2.

صفحه 11:
۵ 2 1 6 5 q ‏لكك‎ dd) SACS ACS ACs: COS hs cai CPS sD) LOOX MOCO R Ss SCO Rss 2a ‏جع‎ ‎(59 4 Bsc!) > Figure 6.6 g 000 00 Cees ‏لكك كك‎ (4 اک منت هت ‎(OSTA‏ = Roll forward one week =" Higher demand over weeks 1-12 — Total was 120, now is 155 ™ Need to revise MPS

صفحه 12:
و۳۳۱۳ Figure 6.7 e@q¢gqg eG Gaba a Ci) A) CD CA) CD IH IS CI IG GS ake (Bren) | ) a) dd ap <a Gap Gea Oca) 3111111111 1-1 Cakerrd (Statice) | Ad = Production planned for week 4 moved ‏عنلا موه - 2 مغ‎ 00 7 = Planned to do 4 batches in 12 weeks, now need 5 - feasible? ™ Changing schedule is expensive, maybe very expensive

صفحه 13:
Order Promising 6.8 = Track # units ordered for each period ™ More orders expected for periods 2,3 =" From on-hand, how many units not yet spoken for? Cea gaa Gg Gada 5 — Fe We We We We Wee 0s ee 0s ee ceca == ewe ke akble rte) [aad © ‏هك عه عه‎ Ci ۹۹ <ap fea [eal Ors ۹۹ ۱1۹۰۱۷۱۱5

صفحه 14:
Available to Promise مه ‎Backlog of 10 orders over first 3‏ ™ weeks: 5,3,2 — Actual firm customer orders, not forecasts. — Total shipments expected to be 5 in early ۷۷66 = 20 units on hand. = 10 units are available to promise = 20 units on hand have to cover all demands until next production

صفحه 15:
Week 1 Demand is 10 ™ Suppose demand is 10 in week 1. — Orders for 5 week 1 units were received in week 1. — Already had firm orders for 5 for wk 18 ™ Increase forecasts of future week shipments. ™ Started period 1 with 20, demand was 10, ended with 10.

صفحه 16:
Order Promising - Fig. 6.9 = 9 9 6 a 6 40 9 9 (Forecast AG 6G IG] GG] 6G] dG dG. ag dG ag ag 4 Crna 6 6 6 Qrailable (Gadiaa) | QD GD dG 0 6 00 150 0 ore 3 En 5۱۱1۲۳2۱ 1 oes ao ga qd aaj da qa a Og hua ‏دی کی‎ | dG Received more orders for periods 2-4 Period 2 ending inventory would be 0, so have to produce in week 2. (10+30) - (5+5+2)=28 Order backlog went from 10 to 12- factor in revising forecasts?

صفحه 17:
‎inventory plus production is 10+30‏ ات ‎We have orders for 5 in period 2 ‎It looks like we could accept orders for up to 35 ۲۳2۵۲۵ ۱۱۳۲5 1۱ ۰ ‎But we can’t. We've promised 7 of those units to weeks 3&4. ‎Selling more would mean we have to expedite another shipment, like we just did, but which we really, really don’t want to have to do. ‎So, not safe to assume we can easily expedite in short term ‎ ‎ ‎8 8 © qa ad aaj ad ag Cae ad ag ad ad ad ag ag adag ad ag ag oe 98 6 ‏انیت‎ aad alent den det dai gd Cora 88 ‏نه‎ ee 06 ad dal d dat day day @g Cae een | 00 ‎ ‎ ‎ ‎ ‎ ‎ ‎ ‎ ‎ ‎ ‎ ‎ ‎

صفحه 18:
Calculating “Available” ™ Current batch plus on hand ™ Minus the greater of Forecast and confirmed orders ™ Previous available + MPS - (greater of forecast or orders)

صفحه 19:
Calculating ATP ™ Calculated in current week and any week with MPS>0 — Current period: on-hand plus any current period MPS, minus all orders in that and subsequent periods until next MPS — Later periods: MPS - all orders until next MPS — ATP = MPS in weeks 5, 8, 10, 12

صفحه 20:
ATP: Future ‏ات‎ Oe Wk 10 ATP goes to 0, 5 additional units need to come from ATP for previous MPS ™ Week 8 MPS goes to 25 = Set MPS for 11? We need to do ‏أطاع ممه‎ 07 € 6 a5 5۳/6 ‏ات ادوس‎ ems Orders ‏ا‎ [= Cee Cre mks he ‏ها‎ ‎Ca iss] 900 8 0 ‏اک‎ ‎ORs adda ada da da ONIN CAR AE RCD,

صفحه 21:
Consuming the Forecast Fig. 6.10 ™ Go back to Fig. 6.9 " Can we accept following orders? 1. 5 units week 2 2. 15 units week 3 3. 35 units week 6 4. 10 units week 5

صفحه 22:
ala ‏اام اك تم‎ 5 in week 2? 5 © © © 2 © © 000 00 8 AQ, dO dq dG ag ag 49 19 9 ‏عات‎ ‎is RCO bs) 1 5 eee ۹ ۹ co وا 0 forecast Orders Cue Cae) ۳ ORG ات سید له ™ 5 in week 2 - must come from ATP in .2 كاعع الا Le Na a eo 0) ao ™ Reduce ATP to 23, add order

صفحه 23:
PS 2 ۵ 000 06 5 in week 2? OK 2 2۱ ۵ CGorecust dG dG dQ dQ dG dg ag a Orders aq Cee Cue ke he RCORe Oke DESKS )7 ‏م‎ oD 91 MPG Fs) OO) Ke 1) ‏الى اللكاه4 الى‎ Og kad (stunting) 0 = Reduced ATP to 23, add 5 to 01015

صفحه 24:
airy ‏اح‎ ‏حم‎ ات 15 in week 3? 552 dq a 0 ag ad ad ad ag ag ag agg 152 0 6 90 © 90 50 00 0ه لم ‎ay ٩0 [a0‏ عه 0 30 0 0 50 0 0 20 000 (Forecast Orders Cee one) CAG ORS 0 cabins?) = 15 in week 3 - needs to come from ATP in week 2. = ATP in 2 is 23, so it works

صفحه 25:
_15 in week 3? OK EG 1 G dadaajadad Cee 00000100 00.007 08 026 026 02 06 06 ‏ع0‎ ‏دل‎ Cae! raiable (Gadiay) [AN dc] Gavad -<dagd -dad -Gad -< Cis 6 0 a jal [a Go ‏ا ا ادع‎ 2۱ da dmg a Oa kuad (stuntiag) | dD) ™ Reduced ATP to 8, added 15 to “Orders” = Notice all future ending levels went down by 10 ™ Consider moving MPS from 5 to 4. — Depends on marketing’s beliefs about 4. RE Se feta Me et er ae a ‏و‎

صفحه 26:
دا 35 in week 6? ۱20۳2۳ 212 1 Forecast dd dG dG dO dg dg dg aGag Oia qgay gq Qvaitable (Gadivy) | QDdID Gandd -Gdag -Gag Orr 6 0 0 ‏الك‎ ‎20 ‏_0ه‎ 0 0[ 91 0( 00 91(_ 0( 0 (ONIN ‏ل‎ | 0 = ATP in week 5 is only 30. ™ How could this work?

صفحه 27:
_35 in week 6? OK (GL el ken SLs 6 8 4 mC RCS mS, ‏فد متا‎ ۱۱۹۹۱۹ ۹ ۹2 2 06 06 Orders CORSE, ‏ات‎ ‎vuilable (Gadivy) | QD 00 0 50( -9 -20( 216 -30( -.19 -20( -9 -ap Cag ‏اللكا الاک 0 ی‎ is) 0005 ‏_0مهك‎ 0 00 9 ¢ agmam am oa ‏تفت له‎ | IG = 30 from ATP in week 5, which goes to 0. ™ Need 5 more ATP from week 2, ATP in 2 goes down to 3. = But it would only be prudent to approve it if: ® You think this 35 represents all the demand you'll see = (Those forecasted other orders are not coming), OR ™ You can adjust the MPS to meet forecasted demand = No room to accommodate 10 in w 5, could do in week 8

صفحه 28:
Fig. 6.10 5 © 6 6 8 6 8 0000| 086108 © Caan ad daa ag ag ag ag ag ag ag ag ag xn a 4 a aq, vailable (Gadivy) [AO O 20 -9 -20 -09 -60( -49 -00 -16 -90 5 one 9 0 90 0 0 Wao) 0 460 ¢ 00 OR OD 0 0 ‏(وورسع) معط و6‎ | 0 ™ Roll one week forward in time = What to do about Available < 0? — Maybe nothing. forecasted sales may not appear — If they do, we’re in trouble - produce more,

صفحه 29:
Bill of Materials ™ Bill of Materials - Parent-child diagram that shows what goes into what. = Used to make sure enough parts for production plan ™ Each part has LT, ordering policy ™ One BOM for every end product 1 Frame Assy ‘Component 5 Hubs & Rims

صفحه 30:
BOM formats " Bidglt:¢eveOBOM only shows one = kiyer down. — Frame Assembly Whe« Tires. — Wheel Assembly " ‏اعع نالا‎ ‏تور راز‎ — Spokes "Tires

صفحه 31:
Low-Level Code 1 اه : Numbers = Lowest level in structure item occurs = Top level is 0; next level is 1 etc. ™ Process Os first, then 1s = Know all demand for an item = Where should blue 99

صفحه 32:
LLC Drawing = Item only appears ine in one level of LLC ° drawing ‏4ك وت تعد لا‎ understand 2 = Simplifies calculations

صفحه 33:
Final Assembly Schedule ™ Master Production schedule is anticipated build schedule ™ FAS is actual build schedule — Exact end-item configurations

صفحه 34:
Schedule Stability ™ Stable schedule means stable component schedules, more efficient ™ No changes means lost sales ™ Frozen zone- no changes at all ™" Time fences — >24 wks, all changes allowed (water) — 16-23 wks substitutions, if parts there (slush) — 8-16 minor changes only (slush) — < 8 no changes (ice)

صفحه 35:
HW ™ Pages 168-181, 183-188 " 00: 5 = Problems: 1,4,6,8

39,000 تومان