صفحه 1:
In the name of
God
Piping in Teton Dam
صفحه 2:
Introduction
on
Piping
صفحه 3:
HYDRAULIC ۵
= Darcy’s Law predicts that under normal
conditions, the volume of water that flows
through a porous medium increases in
direct proportion to the hydraulic head
= Terzaghi (1929) asserted that the moment
that the seepage pressure becomes equal
to the force of gravity (effective stress),
the discharge increases abruptly,
because soil particles begin to be lifted
apart and dispersed.
صفحه 4:
CRITICAL HYDRAULIC GRADIENT
= Terzaghi defined the critical hydraulic gradient
as that value of pressure head which equals the
ratio between effective normal stress acting on
the soil and the pore water pressure. When
these values become equal, the effective stress
becomes zero because the seepage pressure
equals the submerged weight of the soil.
= The percolating water can then lift particles of
soil into suspension and transport them.
« This process is known as hydraulic piping
صفحه 5:
GENERAL ASPECTS OF THE CRACKSTOPPER THEORY
Zowe ABOVE
TaLWATER musT BE A
Aypotherrca/ crack
upstream ni chy care
filters
Jwo EssenTiat ELEMENTS
7. CRACK Won'T GET LARGER
2. CRACK WILL PLUG WITH FIL7ER MIL.
— Wo GUARANTEE oF VaLioITy —
= Graded filters are intended to restrict the
migration of fines on either side of the
impervious clay core of an embankment dam
صفحه 6:
GRADED FILTER CRITERIA
100)
Suitable filter
material
Percent passing
«| /
005 01 02 OF 10 20 5.0 10
Sieve opening. mm
= Filtration criteria were initially explored by Terzaghi in 1922, then
refined by experiments of the Bureau of Reclamation, published
in 1947 (shown here). The purpose of filters is to prevent
migration of soil particles under a positive hydraulic gradient; a
process referred to as ‘hydraulic piping”.
صفحه 7:
Some Reasons of piping
Weak controlling during construction
Low density of concrete adjacent the pipes
Cohesionless or less cohesion soils Dam-foundation
interaction
Cracks due to Heterogeneous soils foundation and
embankment
Pipes cracks
Sliding in dam
Waves effects in upstream
Caves which are dugged by animals
Drying the surface of embankment during construction
Drying the downstream
Downstream deformation
Arching effect
Layers with high permeability
¥ Improper compacting layers
ANN
5
باج بك ابوك 1 بد
صفحه 8:
ال رمه(ا) مدص ]”
duce GS, (OPO
۰ 06 hited
Cruel) sound euqarertoy اس
* OCuuse oP Pothine
— Durn Pil toodequately posepacted, tow dey
= Pravtuned bedrock cbutwe
— Cxcessive ما vo yout barrier
— Cipro erosiog of tucks by teckiccy رت
صفحه 9:
Geology
characterization
&
Compaction
Materials
صفحه 10:
= Teton Dam was built on the Teton River, one of the principal
features of the Teton Basin Project of the US Bureau of
Reclamation funded in 1964. It was intended to supplement
irrigation of 112,000 acres of farm land in the Upper Snake River
Valley and generate 16,000 Kw of electricity. The plain above the
gorge is covered by 30 feet of wind-blown loess.
صفحه 11:
= Teton Dam was designed with a triple line grout curtain beneath
the earth embankment. But, the grout curtain ended up being
built as a single-line because the grout take was more than double
what had been allotted for the project.
صفحه 12:
bas! is ete ۹
Teton Dam was designed as an earthfill embankment
using wind blown loess as the principal fill material
(seen here as light colored material) with river sand
and gravel (shown as grey color), as the free draining
material.
صفحه 13:
= The dam’s abutments were comprised of a perversely
fractured welded ash-flow tuff (rhyolite), with beds of
lapilli tuff and basalt. Large voids associated with
volcanic fumaroles were detected during construction
صفحه 14:
Prominent and very abundant zones
of low-angle platy joints
Blocky, with closely to widely
spaced moderately to steeply dippi
(30° to 60°) joints dominant, some
low-angle joints in upper part
Blocky, massive, with moderately
abundant near-vertical and low-
angle Joints
A
35۳ ۳6 7
SARS
1 The three principal flow units identified in the dam
abutments are shown here. Unit 2 was observed to be
intensely jointed, with joint apertures of as much as 6
inches. Although many of the largest joints were filled
with concrete slurry, no filter was placed between some
of the open joints and the silty loess fill in the abutment
keyways
صفحه 15:
و
gyre womns اسه
Site سر
LAKE ano srReam Ns f Lane ano STREAM
‘oerosirs مر 0
۱ ۱ 1 Rout = 0.308 Meters
amo PROFILE OF TETON DAM ALONG THE GROUT CAP
= The exposure of so much jointed and blocky rock led to
a major design change, calling for the excavation of
deep seepage cutoff trenches, or keyways, in each
abutment. The grout curtain was extended to the depth
indicated on this vertically exaggerated elevation view.
صفحه 16:
= Asingle line of grout holes was utilized beneath the
embankment because the grout takes were more than
double what had been allotted for the project. The
portion of the right keyway trench that failed is shown
in red cross hatching.
صفحه 17:
اس موی
I
1
aus A cue es
os ai
Fore sissies 1
مه مه of 207 Steet
هد نم
لإالك ۵ ۱۵۵۵۵ 5 او
ایس ی ۳ ۱
اا Zan tea
= Design section through Teton Dam, showing
the five principal fill zones. There were only
three kinds of on-site materials: 1) wind blown
loess (silt); 2) river gravels and sands; and 3)
disaggregated rhyolite tuff from the abutment
excavations
صفحه 18:
compacted
wrth CAT
B25 sheepshat
۶ ۸ ۰
This zone
compacted with
fives af Euclicl
TD-74 dump trucks
SECTION THRU ABUTMENT KEYWAY
FILLED WITH CompacTeD ZONE L FILL
= By changing from the TD-74 dump trucks to the CAT
826, the compactive effort was increased more than
five-fold.
= A much stiffer wedge of fill was thereby created above
lower density fill in the base of the keyway trench
صفحه 19:
When the reservoir filled, the compacted loess would have been
wetted. Low density loess compacted dry-of-optimum moisture
content would be more susceptible to hydrocompaction.
Hydrocompaction-induced settlement may have contributed to
the formation of voids and subsequent hydraulic fracturing
between fill of contrasting density, as sketched here.
صفحه 20:
Failure Sequence
On June 5, 1979
صفحه 21:
= Newly-completed Teton Dam as it appeared in
mid-May 1976, as the reservoir was filling at the
rate of 3 feet per day. The rate of filling is
usually limited to no more than 1 foot per day.
This view is looking towards right abutment
صفحه 22:
a Leakage was initially noted around 7 AM on
Saturday June 5, 1976. This view shows a
dozer being sent down to fill in the hole at
elevation 5200 around 10:45 AM
صفحه 23:
. Sm =<
= The dozer is lost in the expanding hole,
around 11:20 AM on June 5‘. Note turbid
nature of outflow along the abutment
صفحه 24:
ly deteriorating situation as it appeared
around 11:30 AM. A massive hole has
developed in the downstream face of the
embankment and is migrating upward
صفحه 25:
= The hole continues to enlarge and rise toward
the crest of the right abutment. This is about
11:50 AM
صفحه 26:
= Dam crest 666 10 ay at 11:55 AM on
Saturday June 5, 1976. Note increasing
discharge.
صفحه 27:
= Maximum flood discharge emanating from
gap in dam’s right abutment, just after noon
on June 5th, 1976
صفحه 28:
a The final breaching is filmed from a helicopter
that was sent out to warn people downstream
of the imminent failure. Amazingly, one of two
men fishing a half mile downstream survived!
صفحه 29:
A
1$ billiard
Dollar
Flood
صفحه 30:
The flood inundated the
towns of Sugar
Rexburg, only © 6
because of the advance
warning
The loss ended up
costing the federal
government close to $1
billion dollars
At 350 feet high, Teton
was the highest dam to
ever fail
It’s untimely failure
signaled an end to the
era of big dam building in
America
صفحه 31:
= View looking upstream the day after the failure.
The piping failure initiated on the right
abutment, between elevations 5190 and 5230.
صفحه 32:
= Telephoto view of crest of right abutment,
showing remains of the right abutment
keyway, crest embankment and spillway
gates.
صفحه 33:
Post Failure
Analysis
صفحه 34:
» 7 ۳
= Looking at the right abutment and the remains
of the grout cap (arrows). The 60 foot deep V-
notched keyway was swept away during the
flood
صفحه 35:
= Detail of right abutment
keyway area, showing
zone between
elevations 5190 and
5230 underlain by
blocky Unit 2 rhyolite
= This is the fatal
seepage zone, where
water appears to have
jumped across the
keyway, i i
hydraulic p
Zone 1 loess fill
صفحه 36:
= Cross section of right abutment keyway and
crest embankment where the keyway trench was
between elevations 5165 and 5220. The
hydraulic piping appears to have initiated at this
elevation in the keyway, based on observations
the morning of the failure.
صفحه 37:
Soil Properties
« Results from finite element analyses at U.C. Berkeley
showing contours of ratio between vertical stress in
embankment to overburden pressure in the keyway
trench at Sta. 15+00, before wetting of the loess fill. The
analysis suggests the load of the embankment was
being arched across the steeply-inclined keyway trench.
صفحه 38:
و صسه
= Computed values of normal stress on cross section of
right abutment at Sta. 13+70. The highlighted areas are
where the predicted hydrostatic pressure exceeds the
sum of the transverse normal stress and tensile
strength of the Zone 1 fill. These zones would have
been susceptible to hydraulic fracturing.
صفحه 39:
= This shows the enormous cut severing the left
side of the main embankment fill, exposing the
inclined Zone 2 gravel drain. This is how the
dam appears today.
صفحه 40:
= View looking downstream in 1977, after
channelization of the outbreak flood debris
choking the channel.
صفحه 41:
CONCLUSIONS
+ Teton Dam was constructed with numerous
shortcomings, any number of which may have
combined to cause its untimely demise during its
initial filling. These deficiencies include:
« Inadequate grout curtain;
« Lack of filter or sealer between core loess and
open fractures in abutments;
- Excessively steep side walls in abutment keyways,
promoting arching and likelihood of hydraulic
fracturing;
» Gross inconsistencies in compaction techniques
and soil conditioning (wet seams) which may have
led to asymmetric hydrocompaction, which could
have caused open voids to form in the abutment
keyway.
صفحه 42:
CONCLUSIONS
= Acalculated Factor of Safety less than
1.0 does not, in of itself, mean that a
structure failed via the precise
mechanism analyzed.
« All manner of failure mechanisms
should be evaluated without prejudice.
This is difficult to do, for we are all
prejudiced by our life’s experiences.
صفحه 43: